Lakewood Avenue Connector
LOCATION
Atlanta, Georgia
PROJECT SERVICES
Surveying
Civil Engineering
PROJECT HIGHLIGHTS
Bridge length: 131 Ft.
Roadway length: 2457.3 Ft.
Concrete and steel bridge
Bridge was commissioned after a brush fire caused the collapse of its 100 year old predecessor
Provided preliminary and final bridge design for a concrete and steel bridge that was commissioned after a brush fire caused the collapse of its 100 year old predecessor
Provided construction and engineering plans
Provided right of way location
Bridge services approximately 8,500 commuters daily by connecting McDonough Boulevard and Milton Avenue